Construction risk register example

All posts

A worked construction risk register: eight real project risks, from ground conditions to subcontractor insolvency, with scores, owners, controls and triggers.

Most construction projects have a risk register. It gets built at tender, attached to the bid, maybe looked at once in the kickoff meeting, and then it quietly dies in a SharePoint folder while the actual risks get managed in site meetings, emails and people's heads.

That's a shame, because a register that's actually kept up is one of the most useful tools a project team has. It's where you spot the subcontractor that's wobbling or the long-lead item that's slipping before they turn into a claim.

Below is a worked example with eight common construction risks, scored and filled in properly. Use it as a starting point for your own project.

Progress tracking and risk aren't the same thing

Quick distinction, since teams often blur the two. Progress tracking tells you where the project is today against the programme. The risk register looks ahead at what could push it off course.

They work best together, though. Some of the most useful risk triggers come straight from progress data. If concrete pours have been behind for three weeks running, that's your early warning that a weather or labour risk is starting to happen.

The columns that matter

You don't need 30 columns. These are enough:

  • ID and risk statement. Written as cause, event, consequence: "Because X, Y may happen, leading to Z."
  • Owner. A named person, not a department.
  • Inherent score. Likelihood x impact before any controls.
  • Controls. What's already in place.
  • Residual score. What's left with those controls.
  • Actions. What you're going to do next, with dates.
  • Trigger. The signal that tells you the risk is getting closer.
  • Last reviewed. If this is more than a couple of months old, the register isn't being used.

A worked example: eight entries

Scores use a 5 x 5 matrix (likelihood x impact, maximum 25).

IDRiskOwnerInherentKey controlsResidualTrigger to review
C1Because site investigation was limited, unexpected ground conditions may be found during excavation, causing redesign, delay and extra costDesign Manager3 x 4 = 12Additional trial pits in high-risk areas, contingency in the cost plan, design team on call during groundworks2 x 4 = 8Any excavation finding that differs from the site investigation report
C2Late or changing design information may hold up work on site and lead to claims from subcontractorsDesign Manager4 x 4 = 16Information required schedule agreed with designers, weekly RFI tracker, design freeze dates in the programme3 x 3 = 9RFIs older than 10 working days, or any design change after freeze
C3A key subcontractor may become insolvent mid-package, leaving work unfinished and the programme exposedCommercial Manager2 x 5 = 10Financial checks before award, payment monitoring, reserve subcontractor identified for critical packages2 x 4 = 8Late payment of their own suppliers, sudden labour drop on site, or requests for advance payment
C4Material prices may rise sharply after award on a fixed-price contract, eroding marginCommercial Manager3 x 4 = 12Early procurement of volatile materials, price fluctuation clauses where possible, supplier quotes held for agreed periods2 x 3 = 6Supplier price notices, or a monthly cost report showing material overrun
C5Long-lead equipment (switchgear, lifts, plant) may arrive late and delay commissioningProject Manager3 x 4 = 12Orders placed early, factory visits or progress reports for critical items, delivery dates tracked in the programme2 x 4 = 8Any supplier slip on a delivery date, or missed factory milestone
C6Extended bad weather may stop external works and push the programme beyond completion dateProject Manager3 x 3 = 9Weather allowance in the programme, sequence to get the building watertight early, temporary protection2 x 3 = 6External works behind programme for two consecutive weeks
C7A fall from height may cause serious injuryHSE Manager3 x 5 = 15Edge protection and scaffold inspections, permits for roof work, daily briefings, harness checks2 x 5 = 10Any near miss or failed scaffold inspection
C8Delays to completion may trigger liquidated damages under the main contractProject Manager3 x 5 = 15Critical path reviewed every two weeks, extension of time notices issued promptly, mitigation plans for slipping activities2 x 4 = 8Float on the critical path drops below an agreed number of days

A few observations. C8 is mostly downstream of everything else. Ground conditions, design delays and late equipment all feed into it. So it's worth linking C8 to C1, C2 and C5 rather than treating it as its own thing. When one of those moves, check C8 the same week.

C7 keeps an impact of 5 no matter what you do, because the worst outcome is a serious injury. The controls only bring the likelihood down. That's normal for safety risks and nobody should try to argue the impact down to make the heat map look greener.

And C3 is the one teams most often leave off, because nobody wants to say out loud that a subcontractor might go bust. The trigger column helps here. Late supplier payments and sudden labour drops are usually visible weeks before the formal news arrives.

Owner view vs contractor view

This example is written from the main contractor's side. If you're the client or developer, the register looks different. You'd care more about funding, approvals, scope changes, contractor performance and handover. Some risks show up on both registers (C8 is a good example), but the owner and the controls change.

If you're managing a portfolio of projects, you'll also want a portfolio-level register that pulls up the biggest risks from each project. That's where a spreadsheet per project starts to get painful.

Keeping it alive past the tender

  • Review it in the monthly progress meeting, not a separate one.
  • Close risks that have passed (groundworks risks once you're out of the ground) so the register stays short.
  • Move a risk into an issue log once it's actually happened, and record what it cost. This is gold for the next tender.
  • Keep old versions. "What did we think the top risks were at month three?" is a question you'll get asked in a dispute.

Spreadsheet or software?

On a single small project, a spreadsheet based on the table above is fine.

On larger projects, or across a portfolio, Cilver's risk register keeps each project in its own workspace with a roll-up across all of them. Owners get reminders, actions are linked to the risks they treat, and every change is kept with a date and a name, which helps a lot if there's ever a dispute. If your project reporting already runs in Power BI, you can connect the register directly.

Start a 14-day free trial and import this example to try it on a real project.

For more on how to set one up, see our general risk register example or the guide to risk register software for small businesses.

FAQ

What is a construction risk register?

It's a live list of the things that could hurt a construction project's cost, schedule, safety or quality, with an owner, a score, the controls in place and the actions still to do for each one. It's reviewed throughout the project, not just at tender.

Who owns the risk register on a construction project?

Usually the project manager owns the register as a whole, but every individual risk should have its own named owner, such as the commercial manager, design manager or HSE lead.

What's the difference between a risk register and progress tracking?

Progress tracking tells you where the project is against the plan today. The risk register looks forward at what could knock it off the plan. You need both, and the best risk triggers often come straight from your progress data.

How often should a construction risk register be reviewed?

Monthly at a minimum, usually alongside the project progress meeting. High risks and anything on the critical path deserve a look every two weeks, and any risk whose trigger fires should be reviewed right away.

Related in Cilver: Run this register live in Cilver · Connect Power BI to your register · Risk management by industry

Take control of your risk register. Today.

See on your own risks

In 30 minutes, see how Cilver simplifies risk management across your business.

Just have a question? Ask us anything.