A facilities management risk register to copy: eight scored examples covering statutory compliance, contractors, asset failure, PPM backlog and contract KPIs.
Facilities management has a funny relationship with risk. You spend all day preventing things from going wrong, but often the only record of that is a CAFM system full of work orders and a compliance spreadsheet someone updates on Fridays. Ask "what are our top five risks across the portfolio right now?" and it usually takes a few phone calls to answer.
A proper risk register fixes that. Below is a starting register built for FM providers and in-house facilities teams, with eight scored risks you can copy and adapt.
Risk register, compliance tracker or CAFM?
This trips a lot of teams up, so let's sort it out first.
Your CAFM system handles assets, work orders and PPM schedules. It knows a chiller is due a service on Tuesday.
Your compliance tracker lists statutory inspections and whether they've been done: fire alarm tests, sprinkler inspections, lift examinations, water hygiene checks, electrical testing.
Your risk register asks a different question. What could go wrong across this site, contract or portfolio, how bad would it be, what are we doing about it, and is that working? A missed inspection shows up in the tracker. The risk it creates (an unsafe system, an enforcement notice, a contract breach) is what goes in the register.
You need all three. They just do different jobs.
Typical risk categories in FM
These groups cover most of what an FM register needs:
- Statutory compliance. Fire safety, water hygiene, lifts and lifting equipment, gas, electrical, asbestos management.
- Asset condition. Ageing plant, single points of failure, long-lead replacement parts.
- Contractors and people. Subcontractor competence, permits to work, lone working, key staff leaving.
- Contract performance. SLAs, KPIs, service credits and penalties, client satisfaction.
- Data and systems. CAFM accuracy, building management system security, records you'd need in an audit.
A worked example: eight entries
Scores use a 5 x 5 matrix (likelihood x impact, maximum 25). Inherent is before controls. Residual is with the controls you have today.
| ID | Risk | Owner | Inherent | Key controls | Residual | Trigger to review |
|---|---|---|---|---|---|---|
| F1 | A statutory inspection (fire alarm, sprinklers, lifts, water hygiene) is missed or not recorded, leaving an unsafe system and exposure to enforcement | Compliance Manager | 3 x 5 = 15 | Compliance calendar with owner per inspection, evidence uploaded before the task closes, monthly compliance report to the contract lead | 2 x 5 = 10 | Any inspection overdue by more than 7 days |
| F2 | A critical asset (chiller, boiler, main switchboard) fails with no quick replacement, shutting part of the building | Engineering Lead | 3 x 4 = 12 | Critical asset list, condition surveys, spares held for single points of failure, temporary plant hire agreement | 2 x 4 = 8 | Condition survey rates a critical asset poor, or a repeat breakdown within 90 days |
| F3 | A subcontractor without the right competence or permit carries out high-risk work (hot works, working at height, electrical isolation) | Health and Safety Manager | 3 x 5 = 15 | Approved contractor list, competence checks before onboarding, permit-to-work system for high-risk tasks, spot audits | 2 x 5 = 10 | Any permit breach, near miss or new contractor added |
| F4 | PPM backlog grows until assets run past their service intervals and reactive call-outs climb | Operations Manager | 4 x 3 = 12 | Weekly backlog review, resource plan per site, escalation to client when backlog passes agreed threshold | 3 x 3 = 9 | Overdue PPM above agreed percentage for two weeks running |
| F5 | We miss SLA or KPI targets and trigger service credits or a formal performance notice | Contract Manager | 3 x 4 = 12 | KPI dashboard reviewed weekly, early warning to client on known issues, root cause on every failed SLA | 2 x 4 = 8 | Any KPI amber for two consecutive months |
| F6 | A lone worker (out-of-hours engineer, security patrol) is injured and nobody knows for hours | Health and Safety Manager | 2 x 5 = 10 | Lone worker app with check-in timer, out-of-hours escalation contact, risk assessment for every lone-working task | 1 x 5 = 5 | Any missed check-in |
| F7 | Asset data in the CAFM system is wrong or incomplete, so PPMs are missed and audits fail | Systems / Helpdesk Lead | 4 x 3 = 12 | Asset verification at mobilisation, data quality checks quarterly, engineers can flag wrong records from site | 2 x 3 = 6 | Audit finding, or more than a set number of "asset not found" job closures |
| F8 | A key person (contract manager, authorised engineer) leaves and knowledge about the site goes with them | Account Director | 3 x 3 = 9 | Site handbooks kept current, deputies named for key roles, documented handover process | 2 x 3 = 6 | Resignation of anyone in a named key role |
F1 and F3 have the highest residual scores and that's normal. Their impact stays at 5 because the worst outcome is serious harm to people. You can't control your way to a low impact on those. You can only keep the likelihood down, which is why the controls focus on evidence and permits.
F7 looks dull next to the others. It's on the list because so many other failures trace back to it. If the asset register's wrong, the PPM schedule's wrong, and then the compliance report's wrong too.
Running one register across many sites
This is where FM gets harder than most industries. You might have 15 contracts, each with its own client, its own compliance calendar and its own KPIs. Two approaches tend to work:
A register per contract, with a portfolio roll-up. Each contract manager owns their own register. Leadership sees a combined view of the top risks across all of them. This is the most common setup and it matches how FM businesses are run.
A shared set of standard risks plus site-specific ones. Risks like F1, F3 and F6 apply almost everywhere, so you define them once with standard controls, then each site adds its own. This keeps registers consistent without making them identical.
Either way, the thing to avoid is 15 spreadsheets in 15 slightly different formats. That's how a portfolio view takes a week to build.
Keeping it useful
A few habits that make a real difference:
- Review high risks monthly in the contract meeting you're already having. Don't create a separate meeting nobody attends.
- Tie triggers to numbers you already report, like overdue PPM, KPI status and inspection dates.
- After every incident, ask whether it was on the register. If it was, check whether the controls actually worked.
- Share the register with the client. It shows you're watching problems before they land, and that counts for a lot at contract renewal.
Spreadsheet or software?
One site with one owner? A spreadsheet based on the table above is fine.
Once you're running several contracts, it gets painful fast. Cilver gives each contract or site its own workspace with its own owners, and gives leadership one roll-up view across the portfolio. Reviews and overdue actions go to the right person automatically, every change is logged for audits, and you can feed the whole thing into Power BI if your client reporting already lives there.
You can start a 14-day free trial and load this example in a few minutes.
For a broader look at choosing a tool, read our honest guide to risk register software for small businesses.
FAQ
What should a facilities management risk register include?
Each risk needs an ID, a clear risk statement, an owner, inherent and residual scores, the controls in place, any open actions, a trigger for review, and the date it was last reviewed. For FM it also helps to tag each risk to a site or contract.
Is a compliance tracker the same as a risk register?
No. A compliance tracker lists inspections and whether they're done. A risk register looks at what happens if they aren't, and what else could go wrong. A missed inspection shows up in the tracker, and the risk that creates belongs in the register.
Can my CAFM system act as my risk register?
Your CAFM system is great for work orders, assets and PPM schedules. Most aren't built for scoring risks, linking controls and actions, or keeping review history, so FM teams usually run the register alongside CAFM and pull data from it.
How often should an FM risk register be reviewed?
Monthly for high risks and anything tied to statutory compliance, quarterly for the rest, and straight away after an incident, a contract change or a new site coming on board.